Home› Construction›Excavation Volume Calculator
Construction tool

Excavation Volume Calculator

Estimate straight trench volume or a sloped pit/frustum, then convert volume into approximate truck loads.

Calculate excavation volume

Estimate straight trench volume or a sloped pit/frustum, then convert volume into approximate truck loads.

Bank volume—
Loose volume—
Truck loads—
Cubic yards loose—

How the excavation volume calculator works

A rectangular trench uses length × width × depth. A sloped rectangular pit uses the rectangular-frustum formula from top and bottom areas. An editable swell allowance converts in-situ bank volume into a loose-haul volume before truck-load rounding.

Where this construction calculation helps

Use it for preliminary earthwork, spoil-haul planning and comparing trench or pit quantities.

Measurements and assumptions

Soil bulking/swell is highly material-dependent. Groundwater, overbreak, working space, batter slopes and shoring can dominate actual excavation. This calculator is a quantity estimator, not excavation-safety guidance.

Worked example

A 20 m × 1 m × 1.5 m trench contains 30 m³ bank volume. At 20% swell, loose spoil is about 36 m³.

Bank volume, loose volume and haul planning

Keep bank and loose quantities separate when comparing excavation takeoffs with transport capacity. Truck body ratings are usually loose-volume values, while drawings describe in-place geometry. Actual loads may be limited by weight before volume, especially for dense or wet material, so verify vehicle payload limits and disposal-site rules before using the truck count operationally.

Frequently asked questions

What is bank volume?
The volume of soil or rock in its undisturbed in-place condition.
What is swell?
Excavated material usually occupies more volume after loosening; swell is the percentage increase from bank to loose volume.
Can this design safe trench slopes?
No. Excavation safety, shoring and slope requirements need qualified site-specific assessment and local compliance.
Why round truck loads up?
A partial final load still requires a trip, so the planning count is rounded up.